Please find below information in respect of the work to be carried out at the expense of the developer (Taylor Wimpey) associated with their proposed development on the land south of Pool Road. I have attached the Report and the plans in case the link does not work for you.
https://democracy.leeds.gov.uk/ieDecisionDetails.aspx?ID=57380
The Chief Officer (Highways and Transportation) has:
a) Noted the details provided in the Design and Cost report and as shown on the plans included at Appendix 3;
b) Given authority to negotiate the terms of and enter into an agreement with the developer under the provisions of Section 278 of the Highways Act 1980; whereby the highway works associated with the development are carried out by the Council on behalf of the developer;
c) Requested the City Solicitor to advertise a Draft Traffic Regulation Order (TRO) to provide no waiting at any time restrictions (double yellow lines); and if no valid objections are received, to make, seal and implement the new TRO as advertised;
d) Approved adoption of the proposed junction bell-mouth into the development site shown on drawing 733801-LCC-HWT-WD-DR-CH-001 so that it can be added to the Council’s maintenance regime; and
e) Given authority to incur capital expenditure of circa £718,250 consisting of circa £650,000 civil works costs and circa £68,250 staff fees. The costs will be fully funded by the developer through the Section 278 Agreement.