I received the following update this afternoon:
"Good afternoon,
In advance of the Christmas holidays and New Year, please find a brief status update for the S278 Highway Works on the A659 Pool Road, Pool in Wharfedale:
A significant proportion of the S278 highway works have now been constructed. This includes the construction of the new development access, new kerb line buildout on Pool Rd, new footway, and new pedestrian crossing points.
Due to scheduled Yorkshire Water works in this area between January and March 2025, the S278 highway works contractor will demobilise from late December 2024 and will return to complete the remaining S278 highway works from April 2025.
Footway & carriageway resurfacing, road markings, bus shelter works, and any remaining snagging will be carried out from April 2025."